ARIN-prop-221 Simplified requirements for demonstrated need for IPv4 transfers [Archived]
OUT OF DATE?
Here in the Vault, information is published in its final form and then not changed or updated. As a result, some content, specifically links to other pages and other references, may be out-of-date or no longer available.
ARIN-prop-221 Simplified requirements for demonstrated need for IPv4 transfers
Proposal originator: Scott Leibrand
Date: 21 May 2015
Problem statement:
ARIN transfer policy currently inherits all its demonstrated need requirements for IPv4 transfers from NRPM sections 4. Because that section was written primarily to deal with free pool allocations, it is much more complicated than is really necessary for transfers. In practice, ARIN staff applies much more lenient needs assessment to section 8 IPv4 transfer requests than to free pool requests, as 24-month needs are much more difficult to assess to the same level of detail.
This proposal seeks to dramatically simplify the needs assessment process for 8.3 transfers, while still allowing organizations with corner-case requirements to apply under existing policy if necessary.
Policy statement:
8.1.x Simplified requirements for demonstrated need for IPv4 transfers
IPv4 transfer recipients must demonstrate (and an officer of the requesting organization must attest) that they will use at least 50% of their aggregate IPv4 addresses (including the requested resources) on an operational network within 24 months.
Organizations that do not meet the simplified criteria above may instead demonstrate the need for number resources using the criteria in section 4 of the NRPM.
Comments:
a. Timetable for implementation: Immediate
b. Anything else
OUT OF DATE?
Here in the Vault, information is published in its final form and then not changed or updated. As a result, some content, specifically links to other pages and other references, may be out-of-date or no longer available.